Timeline – Frame Erection Week 1

Monday 4th March at 8am

Scaffolding in place and panels stacked ready for the team to arrive and start work.

Tuesday 5th March at 2pm

Tuesday 5th March at 5pm

Glulam ring beam and Easi-joists in place
Glulam ring beam and Easi-joists in place

Wednesday 6th March at 3 pm

1st Floor panels being unloaded directly onto installed floor panels

Thursday 7th March at 9am

1st Floor decking glued into place
1st Floor decking glued into place

Friday 8th March at 9am

Friday 8th March at 12pm

Friday 8th March at 4pm

Starting to cut + place the roof timbers
Starting to cut + place the roof timbers