Discharge of Planning Conditions Requested

An application for discharge of the 13 Planning Conditions has been submitted to Hart Planning on 09 February 2018.

Processing of the remaining Planning Conditions has been lengthy:

  1. The revised documents for Highways Cross Section, Travel Plan and Construction Environmental Plan requested by Hart and uploaded to the public Planning Portal on 29 June 2017 have not been reviewed. We believe that we provided a timely response and complied with the requirement for the “statutory consultee in question to have such information as will enable it to provide a substantive response”, and that the response isĀ  outside of the 21 days duty to respond by statutory consultees
  2. Consultation response of 24 October 2017 had not been uploaded to the public Planning Portal until 30 January 2018 when we requested that this omission was corrected